Key takeaways
- Consultation is needed when qualifying works would cost any one leaseholder more than £250, or a long-term agreement more than £100 in an accounting period[1].
- Each notice stage gives leaseholders a relevant period of 30 days to make observations[1].
- With 1.96 million leasehold homes in England privately rented, many section 20 notices land on landlords whose agents should act on them[2].
- Respond within the 30 days, nominate a contractor if you have one, and plan the landlord's cash flow from the first notice.
What section 20 is, and why letting agents see it
Section 20 of the Landlord and Tenant Act 1985 limits what a freeholder or management company can recover through the service charge for major works and long-term contracts unless it has consulted leaseholders first. The detailed steps are in the Service Charges (Consultation Requirements) (England) Regulations 2003[1].
Letting agents meet section 20 because their landlords are leaseholders. In 2023-24, 1.96 million (41%) of England's estimated 4.83 million leasehold dwellings were privately owned and let in the private rented sector[2]. When a notice arrives at the flat, it is often the tenant who picks it up and the agent who has to make sure the landlord sees it in time.
Make it a standing instruction: any letter addressed to the leaseholder that arrives at a let flat, especially one mentioning section 20, major works or a notice of intention, is photographed and sent to the landlord the same day.
The two thresholds
Consultation is triggered in two situations. For qualifying works, the appropriate amount is a cost that would make the relevant contribution of any one leaseholder more than £250. For qualifying long-term agreements, such as a multi-year cleaning or lift maintenance contract, the threshold is a contribution of more than £100 from any leaseholder in an accounting period[1].
Source: legislation.gov.uk (The National Archives), 2003[1]
Show the data
| Item | Value |
|---|---|
| Qualifying works (per set of works) | £250 |
| Long-term agreements (per accounting period) | £100 |
The test is per leaseholder, not per block. In a small block, a modest roof repair can exceed £250 per flat; in a large block, a much bigger job may not. If the block manager does not consult when it should, its recovery from each leaseholder can be capped at the threshold, unless a tribunal grants dispensation[1].
The stages for qualifying works
Notice of intention
The landlord gives written notice to each leaseholder describing the proposed works in general terms, stating why they are necessary and inviting written observations and nominations of contractors within the relevant period.
Relevant period
The relevant period for each notice is 30 days beginning with the date of the notice. Observations and nominations must arrive within it.
Estimates
The landlord obtains estimates, including one from a leaseholder's nominee where the rules require, and at least one from a person wholly unconnected with the landlord.
Statement of estimates
Leaseholders receive a statement setting out at least two of the estimates, a summary of observations and the landlord's responses, and a further invitation to comment within a relevant period.
Award and reasons
If the contract does not go to a nominated contractor or the lowest estimate, the landlord must give notice of the reasons within 21 days of entering into the contract.
These stages come from Schedule 4, Part 2 of the 2003 regulations, with the relevant period defined in regulation 2[1]. Different, longer procedures apply where a public procurement notice is needed, and a separate set applies to long-term agreements.
Long-term agreements
The second trigger catches contracts rather than projects. A qualifying long-term agreement is one entered into for more than twelve months, such as a cleaning, gardening, lift maintenance or door entry contract, or a management agreement itself. Where the cost to any leaseholder would exceed £100 in an accounting period, the block manager must consult before signing[1]. The steps are similar: a notice of intention, a chance to nominate, a statement of proposals and a period for observations.
For landlords, these agreements matter because they lock in costs for years. When a notice about a long-term contract arrives, check the length, the annual cost per flat and whether there is a break clause, and tell the landlord if the cost looks out of line with what the block pays now.
Reading a statement of estimates
The statement of estimates is the most useful document in the process for a landlord. Summarise it on one page: the contractors who quoted, the amounts, which one the block manager prefers and why, and the cost per flat for your landlord's share under the lease. Check whether professional fees, VAT, scaffolding and contingency sums are included, because they often add a large amount to the headline figure. If the preferred quote is neither the lowest nor the nominated contractor's, expect a notice of reasons after the contract is signed.
What the agent should do at each stage
| Stage | Agent action | Deadline to watch |
|---|---|---|
| Notice of intention arrives | Send to landlord same day; diarise end of relevant period; ask landlord if they want to comment or nominate | 30 days from the date of the notice |
| Landlord wants to respond | Draft observations with the landlord: scope, necessity, timing, access for the tenant | Within the same 30 days |
| Statement of estimates arrives | Summarise the estimates and likely cost per flat for the landlord; check the reserve fund | 30 days from that notice |
| Contract awarded | Note expected start date and tenant access needs; plan rent and cash flow | Notice of reasons within 21 days if required |
| Works begin | Tell the tenant what to expect; log disruption; report problems to the block manager | As per the programme |
Writing useful observations
Observations are most effective when they are specific and early. Landlords, through their agent, might comment on:
- Scope: whether all the listed works are needed now, or some could be phased.
- Evidence: asking for the survey or condition report that justifies the works.
- Specification: whether a cheaper repair is reasonable compared with replacement.
- Disruption: scaffold duration, access to flats and the effect on tenants working from home.
- Contractors: nominating a contractor with relevant experience and insurance.
- Funding: how much is coming from the reserve fund and when demands will be issued.
Example observation: 'The leaseholder of Flat 4 accepts the roof requires repair but asks for the surveyor's report supporting full replacement rather than a repair to the rear slope, and requests that scaffolding on the front elevation be limited to eight weeks given the occupier's tenancy.'
Cash flow and the landlord's tenancy
Major works bills can be large and arrive with limited warning. From the first notice, help the landlord plan: the estimated cost per flat, the likely timing of the demand, whether the reserve fund covers part of it and whether rent held by the agent should be retained to meet it. Put any retention instruction in writing.
Tenants feel the works too. Scaffolding, noise and restricted access affect their quiet enjoyment. Tell the tenant what is planned as soon as you know, give dates, and log complaints. Poor, unclear or delayed communication was listed first among the top issues in lettings disputes at The Property Ombudsman in 2025[3], and the ombudsman decided 61% of cases in the consumer's favour[4].
Disputes, dispensation and the tribunal
If a leaseholder believes the costs are unreasonable or the consultation was defective, the route is usually an application to the First-tier Tribunal (Property Chamber). Landlords can also apply to the tribunal for dispensation from some or all of the consultation requirements, for example where urgent works were needed. Agents should not advise on the merits; refer the landlord to a specialist adviser and supply the documents.
- Keep every notice, statement and estimate on the property file in date order.
- Record when each was received and when it was sent to the landlord.
- Note any observations made and the block manager's responses.
- Keep tenant disruption logs, as they may support a claim about the works.
If the landlord sells the flat while works are under consultation, the buyer's solicitor will ask about them in the leasehold enquiries. A complete file, with every notice and the landlord's responses, helps the sale and avoids arguments about who pays a demand issued after completion.
Example: a roof and window programme
Example (fictional): the managing agent of a 12-flat block in Croydon issues a notice of intention for roof and window works. The letting agent emails it to the landlord of Flat 7 the day the tenant hands it in and diarises the 30-day deadline. The landlord nominates a roofing firm. Six weeks later the statement of estimates shows a cost of about £6,400 per flat. The agent confirms the reserve fund will cover about a third, agrees with the landlord to hold back rent over four months to meet the rest, and sends the tenant the scaffold dates as soon as the contract is awarded.
Frequently asked questions
What is the section 20 threshold?
Consultation is required when qualifying works would cost any one leaseholder more than £250, or when a long-term agreement would cost any leaseholder more than £100 in an accounting period.
How long do leaseholders have to respond to a section 20 notice?
Each notice gives a relevant period of 30 days, beginning with the date of the notice, for observations and nominations.
What happens if the freeholder does not consult?
Recovery from each leaseholder can be limited to the threshold amount unless the tribunal grants dispensation from the requirements.
Does the tenant have to pay towards major works?
No. Service charges, including major works, are the leaseholder's liability. The tenant's rent is not affected by the works bill.
References
legislation.gov.uk (The National Archives) (2003). The Service Charges (Consultation Requirements) (England) Regulations 2003 (regulations 2, 4 and 6; Schedule 4, Part 2) (opens in a new tab) ↑
Ministry of Housing, Communities and Local Government (GOV.UK) (2025). Leasehold dwellings, 2023 to 2024 (opens in a new tab) ↑
The Property Ombudsman (2025). Annual Review 2025 (opens in a new tab) ↑
The Property Ombudsman (2025). Annual Review 2025 (opens in a new tab) ↑