Lettings compliance

Advising landlords on upgrades to reach EPC C

How letting agents can advise landlords on reaching EPC band C: typical measures by property type, the order to do works, voids and the £10,000 cap.

Ava research teamPublished 6 min read

On this page
  1. Why landlords will ask you first
  2. Step one: get an accurate starting point
  3. Typical measures by property type
  4. The order of works matters
  5. Using voids and planning around tenants
  6. Funding, quotes and the cap
  7. Mistakes to steer landlords away from
  8. Explaining upgrades to tenants and applicants
  9. A one-page plan for each landlord
  10. Frequently asked questions
  11. References

Key takeaways

  • The spending cap for reaching band C was cut from a proposed £15,000 to £10,000 per property[1].
  • Start with an up-to-date EPC assessment; an old certificate may understate what has already been done[2].
  • Sequence works fabric first, then controls, then heating, then generation, and use voids for disruptive jobs.
  • Agents already shape landlord decisions: 40% of landlords who raised rent said their agent had advised it[3].

Why landlords will ask you first

Landlords rarely start with an energy assessor. They start with the agent who manages or lets their property, because the agent knows the home, the tenants and the market. That trust is already visible in the data: 40% of landlords in England who raised the rent said their agent had advised them to[3]. Energy upgrades are the next big decision where your advice will carry weight.

The stakes are clear. Privately rented homes must reach band C by 1 October 2030 unless an exemption applies, and the planned cap on what landlords must spend has been set at £10,000, down from a proposed £15,000[1]. Today's cap under the band E standard is £3,500 including VAT[4]. A good agent does not need to be an energy expert, but does need a method for moving each landlord from worry to a plan.

Landlord spending cap for reaching EPC band C
Landlord spending cap for reaching EPC band CColumn chart. Proposed cap: £15,000; Cap after government decision: £10,000.£0£5,000£10,000£15,000Proposed cap: £15,000£15,000Proposed capCap after government decision: £10,000£10,000Cap after government decisionLandlord spending cap for reaching EPC band CColumn chart. Proposed cap: £15,000; Cap after government decision: £10,000.Proposed capProposed cap: £15,000£15,000Cap after government decisionCap after government decision: £10,000£10,000

Source: Propertymark, 2026[1]

Show the data
ItemValue
Proposed cap£15,000
Cap after government decision£10,000

Step one: get an accurate starting point

  1. Check the current certificate

    An EPC is valid for 10 years[2], so many certificates on file pre-date boiler replacements, new windows or loft insulation. Note the date and the band.

  2. Commission a fresh assessment where needed

    If the EPC is old or the home has changed, a new assessment may show a better band and more accurate recommendations. It is the cheapest step in the process.

  3. Read the recommendations

    The EPC lists suggested measures and indicative ratings after each. Use them as a starting map, not a final plan.

  4. Ask for an informed survey for complex homes

    Solid-walled, listed or unusual homes may need a retrofit assessor to identify measures that work without causing damp.

  5. Record the plan

    Note the current band, target band, measures considered, quotes and the timetable on the landlord's file.

Typical measures by property type

Every home is different, but property types share patterns. Use the table to frame the first conversation, then rely on the assessor's report for the detail.

Typical upgrade paths by property type
Property typeUsual first measuresOften needed to reach band CWatch out for
Pre-1919 solid-wall terraceLoft insulation, draught-proofing, heating controlsInternal or external wall insulation, efficient heatingMoisture risk with wall insulation; conservation areas
Inter-war or post-war semi with cavitiesCavity wall and loft insulationBoiler upgrade or heat pump, better controlsPoorly installed old cavity fill
Purpose-built flatHeating controls, lighting, hot water cylinder insulationReplacement electric heating with efficient storage or a heat pumpLeaseholder and freeholder consent for external works
Converted flat in a period houseDraught-proofing, secondary glazing, controlsWall or floor insulation where feasibleShared walls and consent from other owners
Modern house after 2000Lighting, controls, top-up loft insulationOften already near band CLittle room for cheap gains

Example: a two-bedroom 1930s semi is rated band E. The assessor recommends cavity wall insulation, topping up loft insulation, new heating controls and a replacement boiler. The quotes total about £7,800, inside the planned cap, and the projected rating after works is band C. The agency schedules the insulation in the next void and the boiler at the next service.

The order of works matters

Doing the right measures in the wrong order wastes money. A heat pump sized for a draughty, uninsulated house will be larger and more expensive than one sized after the fabric has been improved. Follow a simple sequence.

  1. Fabric first: loft, wall and floor insulation, draught-proofing and, where needed, glazing.
  2. Controls next: thermostats, room controls and timers, which are cheap and lift ratings on their own.
  3. Heating system: replace inefficient boilers or electric heating, sized for the improved home.
  4. Hot water: insulate cylinders and pipework, or replace systems when the heating changes.
  5. Generation last: solar panels or other renewables once the home uses less energy.

Ventilation runs through every step. Insulating and draught-proofing without adequate ventilation can create condensation and mould, which then becomes a repair and health issue. Ask the assessor to confirm ventilation is part of the plan, and add extractor fans or trickle vents if needed.

Using voids and planning around tenants

Disruptive works are far easier in an empty home. Plan the big jobs, such as wall insulation or a heating system change, for the next void, and keep small jobs, such as controls and lighting, for routine visits. When a tenant gives notice on a band D or E home, contact the landlord the same week with the plan and the window available.

Where works must happen with a tenant in place, explain them early, agree dates in writing, and keep disruption short. Tenants are usually supportive of works that cut their bills, but less so of surprise visits. Record every agreed appointment and any refused access. For longer jobs, offer the tenant a clear schedule showing which rooms are affected on which days, and check in by phone after the first day. Small courtesies like these keep goodwill high and reduce the chance of complaints or cancelled appointments that push works past the void.

Funding, quotes and the cap

Before quoting the cap to a landlord, check the current rules. The planned cap of £10,000 for the band C standard[1] is a limit on required spending, not a budget to spend. If relevant measures within the cap would reach band C, the landlord should do them; if every relevant measure within the cap has been installed and the home still falls short, an exemption may be available once the final rules apply.

  • Get at least two quotes for each major measure, and keep them on file.
  • Check whether grant schemes or energy company funding apply to the property or the tenant.
  • Ask installers for the expected EPC impact of each measure, not just the price.
  • Commission a new EPC after the works to record the improvement.

Mistakes to steer landlords away from

Some upgrade decisions look sensible on paper and go wrong in practice. Agents see the consequences first, because tenants ring the branch when the house is cold, damp or expensive to run. Warn landlords about these early.

  • Buying measures for the rating rather than the home, such as solar panels on a draughty, uninsulated house.
  • Installing wall insulation in an older solid-walled home without checking how moisture will escape.
  • Replacing a boiler with a heat pump without upgrading radiators or controls, then leaving tenants with a system they do not understand.
  • Doing works with no new EPC afterwards, so the improvement is never recorded.
  • Choosing the cheapest installer with no guarantee or certification, then losing the evidence needed for an exemption or a grant.
  • Leaving the conversation until notice is served on a tenancy, when the void is already too short for the works.

Explaining upgrades to tenants and applicants

Energy works change how a home is used. A tenant moving from a gas boiler to a heat pump, or from old storage heaters to modern electric heating, needs a short explanation of how the system works best, or bills can rise rather than fall. Add a one-page guide to the welcome pack, walk through the controls at check-in, and ask at the first routine inspection whether the tenant is comfortable with the system.

Better ratings help marketing too. Applicants increasingly compare running costs when choosing between homes, and an improved EPC band is a concrete point a negotiator can make on a viewing. Make sure the new certificate is lodged and the listing is updated as soon as works finish, so the landlord sees the benefit in enquiries as well as compliance.

A one-page plan for each landlord

Pull the steps together into a short document that the landlord can approve. It should fit on one page and be updated as works are done.

Example plan: Property, 14 Elm Road. Current EPC band E, dated 2019. Target band C by October 2030. Measures: loft top-up and cavity wall insulation (next void, expected spring); heating controls (at next gas service); boiler replacement (when current boiler is due, or with the insulation if a void allows). Estimated total within the planned cap. Fresh EPC after the insulation. Review date: six months.

A clear plan turns a vague regulatory threat into a manageable project, and it gives you the evidence that you advised the landlord properly. For the rules themselves, read EPC rules for lettings and the 2030 band C target, and for licensing conditions that may also apply, see HMO licensing: mandatory, additional and selective.

Frequently asked questions

Will a new boiler alone get a home to band C?

Sometimes, if the home is already well insulated. In older homes, a boiler on its own often lifts the rating by less than landlords hope, which is why insulation and controls usually come first.

Should landlords wait for the final rules before doing anything?

No. Fabric measures and controls are sensible whatever the final details, and they are cheaper in a void. Waiting risks a rush for contractors close to the deadline.

Do we need the tenant's consent for works?

Tenants must be given reasonable notice and access must be arranged lawfully. For larger works, agree dates in writing and keep a record, because refused access may later be relevant to compliance.

References

  1. Propertymark (2026). Energy reforms bring tougher penalties for landlords and new support for property upgrades (opens in a new tab) ↑

  2. GOV.UK (2026). Selling a home: Energy Performance Certificates (opens in a new tab) ↑

  3. Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Private Landlord Survey 2024: main report (opens in a new tab) ↑

  4. Department for Energy Security and Net Zero (GOV.UK) (2026). Domestic private rented property: minimum energy efficiency standard - landlord guidance (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo